A can do a work in 15 days. He works for 5 days and then B finishes the rest in 9 days. How many days would B alone take to do the whole work?
A. 12 days
B. 18 days
C. 13.5 days
D. 13 days
A. 12 days
B. 18 days
C. 13.5 days
D. 13 days
Best answer
Answer: C. 13.5 days
Answer: (C) 13.5 days
A does \(\frac{5}{15} = \frac{1}{3}\). B does the remaining \(\frac{2}{3}\) in 9 days, so B alone needs 9 × \(\frac{3}{2}\) = 13.5 days.