Skip to content
doubtly

Find the sequence that minimizes the total elapsed time to complete the following jobs in the order AB. Find the total elapsed time and idle time for machine B :JobsIIIIIIIVVVIVIIMachine A716191014155Machine B121414101657

Q.5 (B) (ii) Find the sequence that minimizes the total elapsed time to complete the following jobs in the order AB. Find the total elapsed time and idle time for machine B :

JobsIIIIIIIVVVIVII
Machine A716191014155
Machine B121414101657

1 answer

Best answer

Answer: Sequence VII \(\to\) I \(\to\) IV \(\to\) V \(\to\) III \(\to\) II \(\to\) VI; total elapsed time = 91 units; idle time for B = 13 units.

Johnson's rule:

  • Smallest time is 5: job VII on A (place first) and job VI on B (place last).
  • Next is 7: job I on A, placed in the next position from the start (job VII's 7 on B is already used).
  • Next is 10: job IV has 10 on both machines (tie for the same job), so it may be placed either in the next position from the start or from the end; we place it next from the start.
  • Next is 14: job V on A goes next from the start; jobs II and III have 14 on B, so they fill the remaining positions from the end (either order).

Optimal sequence: VII, I, IV, V, III, II, VI (VII, I, IV, V, II, III, VI, or placing IV in the sixth position, e.g. VII, I, V, III, II, IV, VI, are alternatives with the same total time of 91 units).

JobMachine A (in–out)Machine B (in–out)
VII0–55–12
I5–1212–24
IV12–2224–34
V22–3636–52
III36–5555–69
II55–7171–85
VI71–8686–91

Total elapsed time = 91 units.

Idle time for machine B = \(91-(12+14+14+10+16+5+7)=91-78=13\) units (5 at the start, then 2, 3, 2 and 1 while waiting for jobs V, III, II and VI).

(Idle time for machine A = \(91-86=5\) units, after it finishes at 86.)

Doubtly AI · 28 Oct 2026 AI-verified · Oct 2026 Report
Was this answer helpful?

Your answer

Log in or create a free account to answer this question.