Answer: Work done = 1960 J
Given: \( m = 20 \text{ kg} \), \( h = 10 \text{ m} \), \( g = 9.8 \text{ m/s}^2 \)
To lift the object we must apply an upward force equal to its weight:
\( F = mg = 20 \times 9.8 = 196 \text{ N} \)
The force and displacement are both upward, so
\( W = F \times s = mgh = 196 \times 10 = 1960 \text{ J} \)
So 1960 J of work is done to take the object to a height of 10 m. (The work done by gravity during this lift is −1960 J, but the question asks for the work done in lifting it.)
Answer: Work done = 1960 J
To lift the object slowly, we must apply an upward force equal to its weight, and the displacement is also upward. So the work done by us is positive.
Given: \(m = 20\) kg, \(h = 10\) m, \(g = 9.8\ \mathrm{m/s^2}\).
Force needed:
\[F = mg = 20 \times 9.8 = 196\ \mathrm{N}\]
Work done:
\[W = F \times s = 196 \times 10 = 1960\ \mathrm{J}\]
This 1960 J is stored in the object as potential energy \(mgh\). The work done by gravity during the same lift is \(-1960\) J, because gravity acts downward while the object moves upward.