Determine the optimal sequence of jobs that minimizes the total elapsed time for the data given below (processing time on machines is given in hours). Also find the total elapsed time and the idle time for three machines.JobsIIIIIIIVVVIVIIMachine A38…
Q.6 (C) (i) Determine the optimal sequence of jobs that minimizes the total elapsed time for the data given below (processing time on machines is given in hours). Also find the total elapsed time and the idle time for three machines.
| Jobs | I | II | III | IV | V | VI | VII |
|---|---|---|---|---|---|---|---|
| Machine A | 3 | 8 | 7 | 4 | 9 | 8 | 7 |
| Machine B | 4 | 3 | 2 | 5 | 1 | 4 | 3 |
| Machine C | 6 | 7 | 5 | 11 | 5 | 6 | 12 |
Solution : Here min A = 3, min C = 5, Max B = 5. Since Min \(C\ge\) max B is satisfied, the problem can be converted into a two machine problem. Let G and H be two fictitious machines \(\therefore G=A+B,\ H=B+C\). The above problem can be written as :
| Jobs | I | II | III | IV | V | VI | VII |
|---|---|---|---|---|---|---|---|
| Machine G | 7 | 11 | 9 | 9 | 10 | 12 | 10 |
| Machine H | 10 | 10 | 7 | 16 | 6 | 10 | 15 |
Using optimal sequence algorithm, the following sequence can be obtained : [ ] [ ] [ ] VI II [ ] [ ]
Work table :
| Jobs | A In | A Out | B In | B Out | C In | C Out |
|---|---|---|---|---|---|---|
| I | 0 | 3 | 3 | 7 | 7 | 13 |
| IV | 3 | 7 | 7 | 12 | 13 | 24 |
| [ ] | 7 | 14 | 14 | 17 | 24 | 36 |
| VI | 14 | 22 | 22 | 26 | 36 | 42 |
| II | 22 | 30 | 30 | 33 | [ ] | 49 |
| [ ] | 30 | 37 | 37 | 39 | 49 | 54 |
| V | 37 | 46 | 46 | 47 | 54 | 59 |
∴ Total elapsed time is = 59 hrs. Idle time for machine A = [ ] hrs. Idle time for machine B = [ ] hrs. Idle time for machine C = 7 hrs.