Chapter: Assignment Problem and Sequencing· Mathematics & Statistics (Commerce) Part 2
If jobs I, II, III have processing times as 8, 6, 5 on machine M1 and 8, 3, 4 on machine M2 in the order M1-M2. Then the optimal sequence is ____.
Q.4 (A)(iv) If jobs I, II, III have processing times as 8, 6, 5 on machine M1 and 8, 3, 4 on machine M2 in the order M1-M2. Then the optimal sequence is ____.
A. I II III
B. I III II
C. II I III
D. III II I