Five jobs must pass through a lathe and a surface grinder, in that order. The processing times in hours are shown below. Determine the optimal sequence of the jobs. Also find the total elapsed time :JobsIIIIIIIVVLathe41525Surface grinder32436

Q.5 (A)(iii) Five jobs must pass through a lathe and a surface grinder, in that order. The processing times in hours are shown below. Determine the optimal sequence of the jobs. Also find the total elapsed time :

JobsIIIIIIIVV
Lathe41525
Surface grinder32436

1 answer

Best answer

Answer: Optimal sequence II → IV → V → III → I; total elapsed time 21 hours.

Johnson's rule (lathe = M1, grinder = M2):

  • Smallest time 1 (job II on lathe): place II first.
  • Next smallest 2 (job IV on lathe): place IV in the next position from the start.
  • Next smallest 3 (job I on grinder): place I last.
  • Next smallest 4 (job III on grinder): place III just before I.
  • Remaining job V takes the middle position.

Optimal sequence: II, IV, V, III, I.

JobLathe inLathe outGrinder inGrinder outGrinder idle time
II01131
IV13360
V388142
III81314180
I131718210

Total elapsed time \(T = 21\) hours.

Idle time on lathe \(= 21 - 17 = 4\) hours; idle time on grinder \(= 1 + 2 = 3\) hours.